Antelope Valley East Kern Water Agency, Westside Water Agency, Phase 2 Well Equipping and Treatment Site Modifications
Water Treatment
Antelope Valley East Kern Water Agency, Westside Water Agency, Phase 2 Well Equipping and Treatment Site Modifications
Palmdale, California
This project involved the installation of two new deep well pumps with associated piping, valves, flow meters and electrical. Including development of two well sites with fencing, sumps, and surfacing. New steel chemical injection manifold and tie into existing storage tank. This project includes new Solar Bee tank mixing equipment and hydro pneumatic skid and controls.
Contract to Date: $29,978,536