Water Treatment Archives - W.M. LYLES CO. /project-category/water-treatment/ Heavy-Civil & Utility Contractor Fri, 23 Jan 2026 23:01:50 +0000 en-US hourly 1 /wp-content/uploads/2024/04/cropped-WML-logo-site-icon-32x32.png Water Treatment Archives - W.M. LYLES CO. /project-category/water-treatment/ 32 32 LADWP, Silver Lake Reservoir Complete Storage Replacement Project /project/silverlake-headwor-ks-reservoir-phase-1/ Wed, 06 Nov 2019 14:13:07 +0000 https://wmlylesco.flywheelsites.com/?post_type=dt_portfolio&p=762 ߲ݴý. has teamed with Webcor Builders and Obayashi Corporation to form Webcor, Obayashi, ߲ݴý, (WOL) a Joint Venture CMAR for the Silverlake Complex Storage Replacement Project. WOL provides construction services and design support for LADWP to meet Federal Water Quality Regulations by con-structing two underground reservoirs and a 96’’ diameter pipeline which will re-place the operational function of the existing Silverlake and Ivanhoe reservoirs. Phase 1 of the project consists of the construction of a 55 million gallon concrete reservoir, connecting piping and a 3,000 foot long 12 foot diameter tunnel.

The post LADWP, Silver Lake Reservoir Complete Storage Replacement Project appeared first on W.M. LYLES CO..

]]>
Silverlake 1

LADWP, Silver Lake Reservoir Complete Storage Replacement Project

Water Treatment

LADWP, Silver Lake Reservoir Complete Storage Replacement Project

Los Angeles, California

Phase 1

߲ݴý. has teamed with Webcor Builders and Obayashi Corporation to form Webcor, Obayashi, ߲ݴý, (WOL) a Joint Venture CMAR for the Silverlake Complex Storage Replacement Project. WOL provides construction services and design support for LADWP to meet Federal Water Quality Regulations by con-structing two underground reservoirs and a 96’’ diameter pipeline which will re-place the operational function of the existing Silverlake and Ivanhoe reservoirs. Phase 1 of the project consists of the construction of a 55 million gallon concrete reservoir, connecting piping and a 3,000 foot long 12 foot diameter tunnel.

Phase 2

Phase 2 consists of the construction of a 60 million gallon concrete reservoir, inlet and outlet piping and installation of 840 lf of 78” diameter steel pipeline.

Contract Amount:
Phase 1 Final Contract Amount: $140,228,983
Phase 2 Contract Amount: $120,000,000
Estimated Final Contract Amount: $300,000,000

Silverlake 4

The post LADWP, Silver Lake Reservoir Complete Storage Replacement Project appeared first on W.M. LYLES CO..

]]>
City of Fresno, Southeast Surface Water Treatment Facility /project/fresno-southeast-surface-water-treatment-facility-2/ Wed, 06 Nov 2019 14:03:20 +0000 https://wmlylesco.flywheelsites.com/?post_type=dt_portfolio&p=757 The SESWTF is designed to treat 80 MDG of surface (river) water from the Kings River to provide potable water to City residents. This greenfield project includes the following processes; flow control struc-ture, pre-treatment basins (flocculation/sedimentation with plate settlers), ozone disinfection structure, and filters (GAC gravity filter). The facility also includes an 8MG treated water reservoir, chemical building, treated water and backwash pump station; washwater recovery and solids lagoons and associated pump stations, electrical substation, operations building, maintenance building, all site utilities (with pipelines up to 84”), landscaping and pavement throughout the site, perimeter block wall and offsite road utilities.

The post City of Fresno, Southeast Surface Water Treatment Facility appeared first on W.M. LYLES CO..

]]>
Fresno 2

City of Fresno, Southeast Surface Water Treatment Facility

Water Treatment

City of Fresno, Southeast Surface Water Treatment Facility

Fresno, California

The SESWTF is designed to treat 80 MGD of surface (river) water from the Kings River to provide potable water to City residents. This greenfield project includes the following processes; flow control struc-ture, pre-treatment basins (flocculation/sedimentation with plate settlers), ozone disinfection structure, and filters (GAC gravity filter). The facility also includes an 8MG treated water reservoir, chemical building, treated water and backwash pump station; washwater recovery and solids lagoons and associated pump stations, electrical substation, operations building, maintenance building, all site utilities (with pipelines up to 84”), landscaping and pavement throughout the site, perimeter block wall and offsite road utilities.

Contract Amount: $162,089,360

Fresno 1 1

The post City of Fresno, Southeast Surface Water Treatment Facility appeared first on W.M. LYLES CO..

]]>
Cal Water, Northwest Bakersfield WTP Increase Net Treatment Capacity Upgrade /project/northwest-bakersfield-water-treatment-plant-increase-net-treatment-capacity-upgrade-project/ Wed, 06 Nov 2019 13:40:22 +0000 https://wmlylesco.flywheelsites.com/?post_type=dt_portfolio&p=747 The Northwest Bakersfield Water Treatment Plant has been unable to achieve design capacity due to high turbidity water reaching the membrane filters which resulted in excessive backwashing and reduced plant output. ߲ݴý. with Black & Veatch as a design sub consultant was selected to provide design-build services to increase plant capacity to 8 MGD (net) and 10.4 MGD (peak) by installing a pretreatment system ahead of the membrane filters. The project included the construction of a 0.42 MG gallon concrete Pretreatment Basin with four Flocculating Mixers, and two trains of Plate Settlers with Straight Line Residuals Sludge Collecting equipment. Mechanical piping sludge draw off from the basins to sewer occurs via a hydraulic head pressure siphon. A new onsite PACL chemical system was installed that included tank storage, chemical feed and flash mixing facilities. The existing earth retention basin was reconstructed and concrete lined to handle the treatment process backwash, system overflows and site storm water runoff. All work was constructed on a very congested site with limited available space for equipment laydown and construction operations.

The post Cal Water, Northwest Bakersfield WTP Increase Net Treatment Capacity Upgrade appeared first on W.M. LYLES CO..

]]>
California Water Service Co. NW Bakersfield 1

Cal Water, Northwest Bakersfield WTP Increase Net Treatment Capacity Upgrade

Water Treatment

Cal Water, Northwest Bakersfield WTP Increase Net Treatment Capacity Upgrade

Bakersfield, California

The Northwest Bakersfield Water Treatment Plant has been unable to achieve design capacity due to high turbidity water reaching the membrane filters which resulted in excessive backwashing and reduced plant output. ߲ݴý. with Black & Veatch as a design sub consultant was selected to provide design-build services to increase plant capacity to 8 MGD (net) and 10.4 MGD (peak) by installing a pretreatment system ahead of the membrane filters. The project included the construction of a 0.42 MG gallon concrete Pretreatment Basin with four Flocculating Mixers, and two trains of Plate Settlers with Straight Line Residuals Sludge Collecting equipment. Mechanical piping sludge draw off from the basins to sewer occurs via a hydraulic head pressure siphon. A new onsite PACL chemical system was installed that included tank storage, chemical feed and flash mixing facilities. The existing earth retention basin was reconstructed and concrete lined to handle the treatment process backwash, system overflows and site storm water runoff. All work was constructed on a very congested site with limited available space for equipment laydown and construction operations.

Contract Amount: $4,394,558

California Water Service Co. NW Bakersfield 4 1
California Water Service Co. NW Bakersfield 2 1

The post Cal Water, Northwest Bakersfield WTP Increase Net Treatment Capacity Upgrade appeared first on W.M. LYLES CO..

]]>
City of Bakersfield, TCP Mitigation Project /project/city-of-bakersfield-tcp-mitigation-project/ Wed, 06 Nov 2019 13:17:45 +0000 https://wmlylesco.flywheelsites.com/?post_type=dt_portfolio&p=739 1,2,3-Trichloropropane (TCP), is an unregulated organic chemical that the State Water Resources Control Board (“SWRCB”) and its Division of Drinking Water have been studying for regulation for several years. In late 2017, the SWRCB approved a maximum containment level (MCL) for TCP of 5 parts per trillion, with compliance monitoring scheduled to commence in January 2018. This fast-track project was required for the City to meet TCP MCL compliance. The City identified 34 well sites that needed treatment with granulated activated carbon (GAC) and ߲ݴý. (WML) was contracted under a progressive design-build agreement for engineering and construction services. WML provided the procurement, installation, carbon loading, and start-up and commissioning of 104 owner-furnished GAC vessels, which expeditiously brought all 34 well sites into full and complete TCP MCL compliance. Provost & Pritchard was engaged to perform engineering and construction management. Construction also included site grading and earthwork, mechanical piping, concrete foundations, backwash tanks and offsite piping.

The post City of Bakersfield, TCP Mitigation Project appeared first on W.M. LYLES CO..

]]>
Bakersfield TCP Mitigation

City of Bakersfield, TCP Mitigation Project

Water Treatment

City of Bakersfield, TCP Mitigation Project

Bakersfield, California

1,2,3-Trichloropropane (TCP), is an unregulated organic chemical that the State Water Resources Control Board (“SWRCB”) and its Division of Drinking Water have been studying for regulation for several years. In late 2017, the SWRCB approved a maximum containment level (MCL) for TCP of 5 parts per trillion, with compliance monitoring scheduled to commence in January 2018. This fast-track project was required for the City to meet TCP MCL compliance. The City identified 34 well sites that needed treatment with granulated activated carbon (GAC) and ߲ݴý. (WML) was contracted under a progressive design-build agreement for engineering and construction services. WML provided the procurement, installation, carbon loading, and start-up and commissioning of 104 owner-furnished GAC vessels, which expeditiously brought all 34 well sites into full and complete TCP MCL compliance. Provost & Pritchard was engaged to perform engineering and construction management. Construction also included site grading and earthwork, mechanical piping, concrete foundations, backwash tanks and offsite piping.

Contract Amount: $23,057,068

Bakersfield TCP Mitigation 1
Bakersfield TCP Mitigation 2

The post City of Bakersfield, TCP Mitigation Project appeared first on W.M. LYLES CO..

]]>
Antelope Valley East Kern Water Agency, Westside Water Agency, Phase 2 Well Equipping and Treatment Site Modifications /project/antelope-valley-east-kern-water-agency-phase-2/ Tue, 08 Oct 2019 18:30:24 +0000 https://wmlylesco.flywheelsites.com/?post_type=dt_portfolio&p=540 Design-Builder of the $126M Tesoro Viejo Water/Wastewater Program. The Program will service the development’s 5,200 dwellings, the 3.0 Million sf industrial and commercial space, schools, hospital, parks, open spaces and trails. The Water/Wastewater Program is being delivered in stages in order to coincide with the anticipated growth of the development.

The post Antelope Valley East Kern Water Agency, Westside Water Agency, Phase 2 Well Equipping and Treatment Site Modifications appeared first on W.M. LYLES CO..

]]>
Water Treatment hero

Antelope Valley East Kern Water Agency, Westside Water Agency, Phase 2 Well Equipping and Treatment Site Modifications

Water Treatment

Antelope Valley East Kern Water Agency, Westside Water Agency, Phase 2 Well Equipping and Treatment Site Modifications

Palmdale, California

This project involved the installation of two new deep well pumps with associated piping, valves, flow meters and electrical. Including development of two well sites with fencing, sumps, and surfacing. New steel chemical injection manifold and tie into existing storage tank. This project includes new Solar Bee tank mixing equipment and hydro pneumatic skid and controls.

Contract to Date: $29,978,536

A9R1lhx4d9 sm0wja 16v0
A9Rmginci sm0wip 16v0

The post Antelope Valley East Kern Water Agency, Westside Water Agency, Phase 2 Well Equipping and Treatment Site Modifications appeared first on W.M. LYLES CO..

]]>